Rolling stock › On order and plannedData updated
2024 Stock
Siemens' Inspiro London design: the first deep-level tube train with air-conditioning, walk-through throughout, with wide double doors only. Cars without bogies ride on their neighbours. Up to 80% of the trains are being assembled at Siemens' new factory in Goole, East Yorkshire; the first were built in Vienna.
2024 Stock · schematic drawing GB Trains · gbtrains.uk/stock/2024/ · CC BY 4.0
You’re welcome to use this drawing
Free to use, change and share, in print or online, under CC BY 4.0. Please credit it:
Drawing: GB Trains, gbtrains.uk, CC BY 4.0Online, link the words to this page. The downloaded file already carries the credit; please leave it on. What the licence covers
Compare with the 1995 Stock and the 1996 Stock →
- Type
- Electric multiple unit
- Builder
- Siemens Mobility, Vienna and Goole
- Built
- 2022 onwards
- In service
- first passenger service expected December 2026 – June 2027
- Lines
- Piccadilly
- Formation
- 9 cars, articulated and walk-through: bogies under five cars only
- Trains in fleet
- 94
- Top speed
- 62 mph (100 km/h)
- Bogies
- Siemens SF 1800 bogies
- Train length
- 373 ft (113.70 m)
- Car height
- 9 ft 4 in (2.844 m)
- Car width
- 8 ft 8 in (2.648 m)
- Train weight (tare)
- 155.4 t empty, 259.7 t at crush load (a nine-car train; TfL)
- Profile
- tube
- Walk-through
- Yes
- Air-conditioned
- Yes
- Seats per train
- 256
- Standing (5 per m²)
- 624
- Total capacity
- 880 (256 seated + 624 standing), TfL's figure; Siemens gives 1,042. Four wheelchair spaces (TfL)
- Status
- Not yet in passenger service. Four trains were testing in London in March 2026, and entry into service has slipped twice from the original end-2025 target. The programme cost is £3.4bn. Peak service will rise from 24 to 27 trains per hour.
Car types
| Code | Car | Length | Doors per side |
|---|---|---|---|
| DM | Driving motor | 51 ft 4 in15.637 m | 2 double |
| IM | Intermediate car, carried on its neighbours (no bogies) | 32 ft 9 in9.978 m | 2 double |
| KM1 | Key motor car | 45 ft 9 in13.938 m | 2 double |
| KM2 | Key motor car (centre) | 45 ft 9 in13.938 m | 2 double |
Sources
How we source figures → · Spotted a mistake? Tell us → (opens in a new tab)
Show the 25 sources from Wikimedia Commons, Transport for London, Siemens Mobility and 4 more
- FOI-3071-2324: 2024 Stock figures Transport for London, 12 December 2023car types, order and lengths, length over body ends (371 ft (113,000 mm)), doorway width, seats and capacity, weights: 155,401 kg tare and 259,719 kg crush a train; four wheelchair spaces (one in each KM1 car, two in the KM2); top design speed 100 km/h (62 mph)
- Piccadilly line Tube train (brochure) Siemens Mobility, August 202494 trains, length over couplings (373 ft (113.7 m), the train length), height, width, floor height, 18 double doors per side, 62 mph (100 km/h)
- Technical data sheet: Metro London (SF 1800 bogie) Siemens Mobility, August 2023SF 1800 bogie, 5 ft 11 in (1,800 mm) wheelbase
- Piccadilly line trains: a journey from 1891 to 2025 Rail Engineer (Malcolm Dobell), 25 June 2021bogies under five cars, trailer bogies under the cabs, inside-frame bogies, floor height
- The new train on the Piccadilly line will arrive in 2025 Rail Engineer (Malcolm Dobell), 19 December 2023bogie and equipment layout diagram (not to scale)
- Piccadilly line upgrade Transport for Londonfleet size, air-conditioning, walk-through, frequency, service window
- Piccadilly line upgrade (Made by TfL) TfL, 29 July 2026service window, capacity +10%
- New Piccadilly line trains delayed further RAIL, 27 February 2026second delay
- TfL has 'credible plan' for new Piccadilly line trains after entry into service delayed again RAIL, 16 March 2026four trains on test (March 2026), programme cost
- Siemens Mobility Limited to be awarded TfL contract to design and manufacture a new generation of Tube trains Transport for London (press release), 15 June 2018contract and options
- 80% of new Piccadilly line trains will be assembled in Yorkshire, Siemens Mobility confirms Global Railway Review, 12 February 2024up to 80% of the trains assembled at Goole; the first built in Vienna (summary)
- L08 886 InnoTrans 2026, DM 48033 (U-Bahn London 2024), Drehgestell.jpg: the cab-end bogie of 2024 Stock driving motor 48033 (photograph, CC BY-SA 4.0) Wikimedia Commons (Falk2), 25 September 2026bogie layout: inside frame, the wheel faces in full, air spring, damper and the shoegear beam on the cab-end trailer bogie (photograph, layout only)
- 'L08 952 InnoTrans 2026, DM 48033 (U-Bahn London 2024).jpg' (photograph: the cab front and its coupler; CC BY-SA 4.0) Wikimedia Commons (Falk2), 25 September 2026the couplers and the joins between cars (layout only)
- London Underground 2024 stock at Acton Town during a test run (March 2026) (2).jpg (photograph, CC BY-SA 4.0) Wikimedia Commons (Fortek67), 7 March 2026the joins between cars: the grey gangway cover, its width, colour and reach (layout only)
- L08 948 InnoTrans 2026, DM 38033 (U-Bahn London 2024).jpg (photograph, CC BY-SA 4.0) Wikimedia Commons (Falk2), 25 September 2026the joins between cars, checked (layout only)
- 'L08 952 InnoTrans 2026, DM 48033 (U-Bahn London 2024).jpg' (photograph: the cab front and its coupler; CC BY-SA 4.0) Wikimedia Commons (Falk2), 25 September 2026the couplers at the cab and car ends: positions, heights and shape
- FOI-1154-2425: The Piccadilly Line Upgrade, presentation to the Permanent Way Institution Transport for London, 12 June 2024, pp. 15-16Siemens' general arrangement: every car's length, bogie centres, door pitch and coupler face (printed); panes, cab door, cab side window, nose outline and underframe (scaled) (set C2024R2)
- FOI-2450-2526: Introduction of 24TS, presentation to the PWI London branch Transport for London, 4 June 2025, pp. 4, 36-37the whole train's elevation (both DMs alike, mirrored); the anticlimbers below 2 ft 3 in (680 mm; set C2024R2)
- London Underground 2024 Stock 38062, Hammersmith.jpg (photograph, CC BY 4.0) Wikimedia Commons (Elshad), 17 January 2026the GA layout checked along the bodyside; the livery's heights; the door leaves' width (set C2024R2)
- Piccadilly Line 2024 Stock Set 31.jpg (photograph, CC BY-SA 4.0) Wikimedia Commons (Hugh Llewelyn), 7 March 2026the GA layout checked on the left side (set C2024R2)
- L08 953 InnoTrans 2026, DM 48033 (U-Bahn London 2024).jpg (photograph, CC BY-SA 4.0) Wikimedia Commons (Falk2), 25 September 2026the cab side's parts, the hatch, grilles, anticlimber block and step (layout only; set C2024R2)
- First 2024 Stock at Ealing Common Depot.jpg (photograph, CC BY-SA 2.0) Wikimedia Commons (OneTrackMinded), 30 March 2025the windscreen, LED ring and centre door; the cab side window on the driver's side (set C2024R2)
- London Underground 2024 Stock 38062, Hammersmith.jpg (photograph, CC BY 4.0) Wikimedia Commons (Elshad), 17 January 2026the DM's underframe, right side: beam, door boxes, cab-bogie bracket (set C2024R3)
- L08 953 InnoTrans 2026, DM 48033 (U-Bahn London 2024).jpg (photograph, CC BY-SA 4.0) Wikimedia Commons (Falk2), 25 September 2026the DM's underframe, right side, close: the boxes, the bracket and its yellow square; the beam's depth (set C2024R3)
- London Underground 2024 Stock during testing at Hammersmith station (1).jpg (photograph, CC BY-SA 4.0) Wikimedia Commons (Fortek67), 28 September 2025the DM's underframe, left side: door-1 boxes and the cab-bogie bracket (set C2024R3)
- KM1 car length: TfL's FOI answer prints 33 ft 8 in (10,268 mm; the motor car's bogie centres, misprinted); Siemens' GA dimensions it 45 ft 9 in (13,938 mm; 1,835 + 10,268 + 1,835), which TfL's 371 ft (113,000 mm) total needs
- Total capacity: TfL gives 880, Siemens 1,042 (both at 5 per m²)
- The 2024 Stock's front outline below 6 ft 7 in (2 m) and the windscreen's edge-on shape: no level photograph of the nose exists, and the GA's line there is the parked wiper (C2024R2)
- The white strip (about 200 mm) and black seal (about 63 mm) between the 2024 Stock's red cab and its cab door: GA widths; two oblique photographs read them differently (C2024R2)
- The 2024 Stock's underframes: the detail drawn is limited by the photographs available; none is level or side on, so positions are read off three-quarter views from above (about 50 mm along) (C2024R3)
- Whether the IM, KM1 and KM2 cars carry the pale boxes under their doorways that the DMs do is unconfirmed (none seen on an IM, a distant glimpse on a KM1, no photograph of a KM2), so none are drawn; the inboard equipment's divisions aren't known on any car (C2024R3)