HS2

Under construction. First trains, Old Oak Common to Birmingham Curzon Street: between May 2036 and October 2039 (Department for Transport, 19 May 2026; checked 13 October 2026).

Britain's new high-speed railway, being built from London Euston to Birmingham Curzon Street and to the West Coast Main Line at Handsacre, near Lichfield. It opens in two stages: Old Oak Common to Birmingham first, then Euston and the link north to Handsacre. The lines beyond Birmingham to Manchester and Leeds were cancelled.

about 140 miles (225 km)Route
4New stations
199 mph (320 km/h)Top speed
23 milesBored tunnel, Old Oak Common to Birmingham, all dug
2036–39First trains expected

Facts

Status
Under construction. About a third of the whole job is done; the civil engineering (tunnels, bridges, earthworks) is about two-thirds done and due to finish by the end of the decade. Track, power and signalling follow.
Opening
Old Oak Common to Birmingham Curzon Street between May 2036 and October 2039; Euston and Handsacre Junction (the full scheme) between May 2040 and December 2043 (Department for Transport, 19 May 2026; checked 13 October 2026). HS2 Ltd’s own ambition, which isn’t a promise: late 2037.
Route
London Euston, Old Oak Common, Birmingham Interchange, then one branch to Birmingham Curzon Street and one to the West Coast Main Line at Handsacre Junction, near Lichfield.
Depots
Washwood Heath, Birmingham (the trains and the control centre); Calvert, Buckinghamshire (maintenance).
Top speed
199 mph (320 km/h), cut in May 2026 from 224 mph (360 km/h); Old Oak Common to Curzon Street in about 45 minutes, three more than at the old top speed.
Signalling
In-cab signalling (ETCS, version 2.1); automatic train operation was dropped in May 2026. Ten trains an hour planned, with room for sixteen.
Operator
Not yet decided: the government is considering how HS2 will fit Great British Railways.
Cost
£87.7 to £102.7 billion (2025 prices); £44.2 billion spent by the end of March 2026.

unverified Some of these figures haven’t yet been checked against an official source or a published history. What’s in doubt ↓

Route 4 stations

HS2 from London Euston to Handsacre Junction, with the Birmingham spur: four stations, the main tunnels, the Colne Valley Viaduct and two depots, in order; below it the main line to scaleLondon Euston6 platformsOld Oak Common6 of 14 platformsBirmingham Interchange4 platformsBirmingham Curzon Streetterminus, 7 platformsEuston tunnel4.5 miles (7.2 km)Northolt tunnels8.5 miles (13.6 km)Colne Valley Viaduct2.1 miles (3.38 km)Chiltern tunnel9.9 miles (16 km)Wendover green tunnel0.9 miles (1.4 km)Long Itchington Wood1 mile (1.6 km)Bromford tunnel3.6 miles (5.8 km)Calvert depotmaintenanceWashwood Heathtrain depotDelta Junctionspur leavesHandsacre Junctionjoins West Coast Main Linebored tunnelgreen (cut-and-cover) tunnelviaductstationjunctiondepotThe strip keeps the order and the labelled lengths, not the spacing; the bar below is to scale.To scale: the main line, Euston to Handsacre, 116 miles (186.51 km) in the 2016 plansEustonOld Oak CommonBirmingham InterchangeHandsacre0 miles20406080100Euston tunnelNortholtColne ValleyChilternLong Itchington WoodDark: bored tunnel. Hollow: viaduct. Green tunnels and the Birmingham spur aren't shown. Tunnels at their 2016 lengths (the Chiltern tunnel 14.9 km; 16 km today).

The strip is schematic: the order is from the Act’s plans and the labelled lengths are figures, the spacing isn’t. The bar beneath it is to scale, from the 2016 plans. The lines beyond Handsacre and Birmingham were cancelled and aren’t drawn here.

Tunnels and the viaduct

StructureLengthState
Euston tunnel (Old Oak Common to Euston)4.5 miles (7.2 km)Being bored since January 2026
Northolt tunnels (Old Oak Common to West Ruislip)8.5 miles (13.6 km)Dug (June 2025)
Colne Valley Viaduct2.1 miles (3.38 km)Built (2025)
Chiltern tunnel9.9 miles (16 km)Dug (2024)
Wendover green tunnel0.9 miles (1.4 km)Shell finished (October 2026)
Long Itchington Wood tunnel1 miles (1.6 km)Dug (2023)
Bromford tunnel (on the Birmingham spur)3.6 miles (5.8 km)Dug (October 2025)

Stations 4

StationHS2 platformsOpensNotes
London Euston6May 2040 to December 2043Beside the existing station. Six platforms, which the Department for Transport says support all foreseeable services now that HS2 ends at Birmingham and Handsacre; earlier plans, for a railway reaching Manchester and Leeds, had more.
Old Oak Common6 (of 14)May 2036 to October 2039West London. Six high-speed platforms below ground and eight on the surface for the Great Western Main Line, Heathrow Express and the Elizabeth line. The surface platforms may open before HS2; no date is agreed.
Birmingham Interchange4May 2036 to October 2039Near the NEC and Birmingham Airport, which a people mover will link, with Birmingham International station.
Birmingham Curzon Street7May 2036 to October 2039City centre, beside Moor Street. The Grade I listed entrance building of the 1838 station is kept.

Trains

Class 895 on order

Ordered
54 ordered, December 2021; the contract is under review
Builder
Hitachi Rail and Alstom (a joint venture): Derby, Crewe and Newton Aycliffe
Top speed
Built for 224 mph (360 km/h); to run at up to 199 mph (320 km/h)
Expected
with HS2's first services, May 2036 to October 2039

The 54 trains were ordered to run on beyond Birmingham to Manchester, Liverpool and Scotland. With the lines north of Birmingham cancelled they must use existing tracks, and Manchester Piccadilly's platforms can't take a pair coupled at 1,312 ft (400 m), so the order is being renegotiated: fewer, longer trains is one option. The Department for Transport says nothing has changed yet (April 2026).

Its length, beside trains you can see today
Class 895, one train around 656 ft (200 m; Department for Transport, 2021); not drawn yet
Class 895, two coupled 1,312 ft (400 m), the length HS2's platforms are built for
Class 390 Pendolino, schematic side elevation
Class 390 Pendolino about 870 ft (265 m) as drawn
Class 374 (Eurostar e320), schematic side elevation
Class 374 (Eurostar e320) about 1,309 ft (399 m) as drawn

One scale, 2 px a metre. Not drawn yet: the cars, doors and front haven't been published, so only its length is shown. HS2, the line →

When it opens

How the HS2 opening date has moved202520302035204020452010 plan, whole of Phase 1December 2026Official window, 2021 to June 20252029 to 2033Since May 2026: Old Oak Common to Curzon StreetMay 2036 to October 2039Since May 2026: Euston and Handsacre JunctionMay 2040 to December 2043HS2 Ltd's own ambition: late 2037Dashed: no longer current. Solid: the windows set in May 2026.

The date has moved before: December 2026 in the 2010 plan, 2029 to 2033 from 2021 until June 2025.

What was cancelled

HS2 was planned as a Y: on from Birmingham to Crewe and Manchester, and to the East Midlands and Leeds. Every part beyond Birmingham and Handsacre has been cancelled. That is why HS2 ends at a junction at Handsacre, why Euston needs only six platforms, and why the trains’ length is being renegotiated.

HS2 as once planned: Phase 1 being built; Phase 2a to Crewe, the western leg to Manchester and the eastern leg to the East Midlands and Leeds, all cancelledto Preston and ScotlandLondon EustonOld Oak CommonBirmingham InterchangeBirmingham Curzon StreetHandsacre JunctionCreweManchester AirportManchester PiccadillyEast Midlands Hub (Toton)LeedsClay Cross link: Chesterfield, SheffieldPhase 1: being builtEuston to Birmingham and Handsacre,about 140 miles. First trains2036 to 2039; Euston by 2043.Phase 2a: Fradley to Crewe, 36 milesAct, February 2021. CancelledOctober 2023. Powers lapsedFebruary 2026; land kept.Golborne link, 13 milesDropped from the bill,June 2022.Phase 2b west: Crewe to ManchesterBill January 2022. CancelledOctober 2023; bill reused forNorthern Powerhouse Rail, May 2024.Phase 2b east: to Toton and Leeds, 123 milesBeyond the East Midlands droppedNovember 2021; the rest cancelledOctober 2023. Land releasedJuly 2025.being builtcancelledcancelled linkexisting line HS2 trains will useSchematic: positions are approximate. Planned stations as at the 2016 to 2022 route decisions.
LegRouteLengthPlanned stationsHow far it gotCancelledNow
Phase 2aFradley (near Lichfield) to the West Coast Main Line near Crewe36 miles (58 km)None new; trains to call at CreweAct passed (Royal Assent 11 February 2021); early works begun4 October 2023Its purchase powers expired on 11 February 2026; the government keeps the land it bought
Phase 2b, western legCrewe to Manchester39.1 miles (63 km) (85 km with the Golborne link)Manchester Airport; Manchester Piccadilly (new high-speed platforms)Bill introduced 24 January 20224 October 2023The bill was reused in May 2024 for part of Northern Powerhouse Rail, Millington to Manchester Piccadilly; its route stays safeguarded
Golborne linkFrom the western leg near Knutsford to the West Coast Main Line near Wigan13 miles (21 km)NoneIn the 2022 bill6 June 2022 (taken out of the bill)Room left for a future link
Phase 2b, eastern legPhase 1 near Coleshill to Leeds, with a link at Clay Cross for Chesterfield and Sheffield123 miles (198 km)East Midlands Hub (Toton); Leeds (city centre)Route chosen 2016 to 2017; never a billThe East Midlands to Leeds on 18 November 2021 (the Integrated Rail Plan); Birmingham to East Midlands Parkway on 4 October 2023Safeguarding lifted in July 2025; the land is being sold, starting with 558 properties

The government keeps the land between the West Midlands and Crewe and says it intends, in the long term, a new line between Birmingham and Manchester, which will not be a revival of HS2.

History 8

  1. Royal Assent: the High Speed Rail (London - West Midlands) Act.
  2. Main construction begins.
  3. The government orders 54 trains from Hitachi and Alstom, for about £2 billion; first passengers then expected between 2029 and 2033.
  4. The lines beyond Birmingham to Manchester and the East Midlands are cancelled.
  5. The Transport Secretary tells Parliament that HS2 cannot open by 2033.
  6. The Colne Valley Viaduct, Britain's longest railway bridge, is finished.
  7. Tunnelling from Old Oak Common to Euston begins, the last major tunnel.
  8. The reset: first trains between May 2036 and October 2039, Euston by 2043; top speed cut; cost £87.7 to £102.7 billion.

Sources

How we source figures →  ·  Spotted a mistake? Tell us → (opens in a new tab)

Show the 30 sources from HS2 Ltd, Wikipedia, Department for Transport and 8 more
unverified
  • The route's length in kilometres (225 km): worked out from HS2 Ltd's 'about 140 miles'
  • The to-scale bar: read by eye from the 2016 Parliamentary plans, each Work added end to end, three of the joins assumed; the Chiltern (14.9 km) and Bromford (2.9 km) tunnels are shorter there than today's 16 km and 5.8 km
  • The cancelled phases: the Golborne link's removal, the western leg's bill reused for Northern Powerhouse Rail and the October 2023 cancellation are from trade press reporting government statements; the 2016 to 2017 route decisions from HS2 Ltd's factsheets as summarised in search results
  • The eastern leg's length (198 km, 123 miles): HS2 Ltd's 2017 factsheet as quoted in search results, not read